Can Goa Speed up Real Estate Approvals After Six-Month Delays?
Photo: Fredericknoronha / Wikimedia Commons (CC BY-SA 4.0)
Key takeaways
- Credai reports approval delays of up to six months for real estate projects in Goa.
- Land-conversion Sanads require developers to visit three to four departments despite an online process.
- Water approvals pass through four engineering levels and ministerial clearance.
- Fire NOCs now have five-year validity, and some panchayats offer online applications.
Credai has urged the Goa government to accelerate real estate project approvals, with developers reporting delays of up to six months for essential permissions, according to Constro Facilitator. The Confederation of Real Estate Developers’ Associations of India has urged the state government to put its ease-of-doing-business reforms into practice in both letter and spirit (ETRealty.com).
"The entire process takes about six months. It should be simple: either the infrastructure is available or it is not available," — Mohidin, CEO and founder of Mohidin Properties and Holdings.
Why are approvals taking so long in Goa?
Builders explained that water-availability certificates and power-supply NOCs can remain pending for months as applications pass through bureaucratic layers and sometimes require ministerial clearance. Departments also interpret government instructions differently, creating further administrative obstacles.
Developers identified the Sanad certificate needed for changing agricultural land to non-agricultural use as a central issue (The Times of India). Obtaining a conversion Sanad requires visits to three to four departments for NOCs and in-person follow-up with each one, even though the procedure is presented as online. In practice, it does not proceed online and cannot be completed without physical follow-up. As Credai-Goa secretary, Avez Mohidin said that obtaining land-conversion NOCs requires visits to three to four departments, although the procedure is intended to be online.
Mohidin said the 45-day timetable promised by Chief Minister Pramod Sawant for Sanad documents has not been reflected in builders’ experience. Credai wants time-bound approvals across departments and consistent implementation of the state’s ease-of-doing-business reforms, as well as fewer unnecessary administrative procedures, better coordination between departments and predictable timelines.
Which approvals are causing the biggest delays?
Before a water-feasibility application reaches the minister, it must clear the assistant engineer, executive engineer, superintendent engineer and chief engineer. After ministerial approval, the application returns through those same engineering levels.
Mohidin described that route as taking about six months. He argued that the decision should be based simply on whether the necessary infrastructure is available.
Credai has said that, despite infrastructure-tax payments, developers are forced to procure electricity transformers and cables. The association’s warning is that delays are affecting construction schedules and increasing compliance-related costs, as Constro Facilitator reported.
- Land-conversion Sanads require physical follow-up with three to four departments despite being presented as an online procedure.
- Water-feasibility applications pass through four engineering levels and ministerial approval, taking about six months.
- Developers say infrastructure-tax payments do not remove the need to purchase transformers and cables.
Can existing properties face unexpected conversion costs?
Rajesh Sheth, Credai president and Jaibhuvan Group director, pointed to a Panaji developer who was renovating an old building. The developer was asked to obtain land-conversion permission even though the plot was already developed and located within the city.
Sheth said that a penalty calculated on the property’s current valuation was also payable because revenue records still treated the land as agricultural.
For off-plan buyers examining broader pricing and handover issues, the site has separately covered how a Surrey presale resale reflects buyer pricing.
Which reforms are already working?
Sheth acknowledged improvements arising from the government’s deregulation exercise. Sheth noted that deregulation has extended fire NOC validity to five years, lengthened the validity of Pollution Control Board certificates and allowed some panchayats to introduce online applications.
Credai nevertheless wants these measures applied consistently across departments. Its stated priorities are fewer unnecessary administrative procedures, better coordination between government departments and predictable approval timelines.
The scale of the unresolved problem remains substantial: real estate project approvals have been delayed by up to six months.
Sources
- Credai urges Goa government to speed up real estate project approvals — realty.economictimes.indiatimes.com, 2026-11-06
- CREDAI Urges Goa Government to Speed Up Real Estate Project ... — constrofacilitator.com, 2026-11-06
- Credai urges govt to speed up real estate project approvals | Goa News — timesofindia.indiatimes.com, 2026-11-05